Friday, September 10, 2010

Bring on the Shingles

We are finally ready for shingles! Preparing the roof was a long process because of the many layers - 2 sheets of insulation, followed by OSB, and topped with tar paper. There is a picture below of a cross section that shows that. Plus, the dormer had to be framed. I am excited to see that last piece go up on the house. It gives the front a more balanced look and there is lots of room on the inside of the dormer (see the second picture).
The rough-in plumbing is finished and has passed inspection. The fourth picture is the plumbing work for the basement (that is John and Pop's handy framework). The electrician is just about finished up with the electrical boxes,and now the HVAC sub is on the scene. The vents have been cut and duct work started.
My favorite new addition is the porch railing. Bill has been hand making it at home, since he is no longer working on site, and a few sections were completed today. Now I just need my rocker :)