Wednesday, June 30, 2010
Logs Arrive
The truck arrived bright and early on the 29th. The logs are now unloaded and stack strategically around the property. Don, our representative from the log supplier BPB, was on site today, helping the crew get the first few courses set. Only 13 more to go!
Friday, June 25, 2010
Decking Done
Logs are scheduled to arrive Tuesday, which means they will start setting them Wednesday or Thursday - can't wait!
Thursday, June 24, 2010
Decking started
I think we picked the hottest and stormiest summer to build a house, but the guys are perservering. They finished up the porch framing and started laying the decking. They completed the dining room side and half of the backside. It looks like their materials are ready to go for tomorrow (and no rain is in the forecast). Bill said that the logs are set to arrive Tuesday (Jack's birthday-just what he wanted;)
Wednesday, June 23, 2010
Porch
The crew is currently working on framing up the wrap around porch. So far they have completed the front, garage side, and have finished most of the back side. The remaining side should be easy because it is fairly level with the ground, so no scaffolding. The decking should also go quickly. They anticipate being finished by the end of the week, which means logs are next!!!!
Thursday, June 17, 2010
Covering up
Wednesday, June 16, 2010
Floor
Tuesday, June 15, 2010
Rooms
Framing up the basement continues to move along. You can actually tell there are two distinct rooms now. The wall dividing the garage and the family room is up, which makes it very easy to visualize the space. In the pictures, you can see the large beams are now in place. They are essentially going to support the whole house (along with some posts that will be added later). You can also see the 'view' out the family room door. The last picture is a visitor who stops by the job site almost daily, I guess for a little breakfast with the crew.
Friday, June 11, 2010
Framing Continues
Wednesday, June 9, 2010
Framing